Anthropic began trading on Nasdaq Thursday after pricing its initial public offering at $83 a share. The offering totaled about $81 billion before underwriting discounts, including shares sold by existing investors. But one of the clearest examples of the real estate behind the IPO is in Hawesville, Kentucky, where the company signed a lease in July for two decades of data center capacity at a former aluminum smelter. IPO prospectus · Trading debut
TeraWulf, the developer, puts contracted revenue from the initial 20-year term at roughly $19 billion. The lease covers three buildings and about 401 megawatts of capacity for computing equipment. TeraWulf says construction is underway, with the first building targeted for late 2027 and the third for the second quarter of 2028. The $19 billion is revenue contracted over the lease term, not the cost of constructing the campus or rent already collected. TeraWulf’s November project update
Why the former smelter matters
The project can reuse the switchyard and transmission lines that once served the aluminum plant, according to the utility’s filing. TeraWulf reports 482 megawatts of approved electric service, a separate measure from the 401 megawatts contracted for computing equipment. Google has agreed to backstop certain Anthropic obligations to support project financing. Under the agreements, each backstop takes effect when the final data hall under the corresponding lease commences service. Subject to the agreements, Google can take over the relevant lease or, in certain circumstances, allow it to terminate and pay a fee. Utility filing · Credit support filing
The property deal is only part of the bill
In its November 11 European prospectus, Anthropic disclosed about $900.9 billion in purchase and lease commitments, nearly all tied to computing and infrastructure. That total includes more than real estate. Its prospectus says it can contract for building capacity before making larger commitments for the chips inside. It had already announced a $50 billion U.S. infrastructure plan with Fluidstack in 2025, initially naming Texas and New York. That plan predates the IPO and is separate from the Kentucky lease. Anthropic’s 2025 announcement European prospectus
In Kentucky, the next milestone is physical: whether the first building is delivered on schedule. The tenant commitment, approved electric service and conditional credit support are documented. The computing capacity still has to be built.