Friday, November 20, 2026Commercial real estate news
About The Basis
the basis.

Commercial real estate.
The full picture.

Saved storiesSubscribe
Rates
RATE WATCHDaily benchmarks10-year Treasury5.07%-3 bpAs of Nov 185-year Treasury4.89%-1 bpAs of Nov 18SOFR3.90%-2 bpAs of Nov 18Effective Fed funds3.88%UnchangedAs of Nov 18
STATE MARKET PULSESeptember 2026 · BLS · Monthly
New YorkJobs YoY +0.2%Unemployment 4.3%FloridaJobs YoY +0.6%Unemployment 4.4%TexasJobs YoY +1.1%Unemployment 4.4%CaliforniaJobs YoY +0.7%Unemployment 5.1%New JerseyJobs YoY +0.1%Unemployment 4.2%North CarolinaJobs YoY +1.3%Unemployment 3.4%AlabamaJobs YoY +1.0%Unemployment 3.5%AlaskaJobs YoY +1.2%Unemployment 4.3%ArizonaJobs YoY +0.6%Unemployment 4.9%ArkansasJobs YoY +0.9%Unemployment 3.9%ColoradoJobs YoY +0.4%Unemployment 4.1%ConnecticutJobs YoY +0.9%Unemployment 5.1%DelawareJobs YoY +0.3%Unemployment 4.6%District of ColumbiaJobs YoY -3.5%Unemployment 5.6%GeorgiaJobs YoY 0.0%Unemployment 3.3%HawaiiJobs YoY +0.1%Unemployment 2.8%IdahoJobs YoY +1.0%Unemployment 3.6%IllinoisJobs YoY +0.2%Unemployment 4.6%IndianaJobs YoY -0.4%Unemployment 3.4%IowaJobs YoY +0.3%Unemployment 3.2%KansasJobs YoY +0.3%Unemployment 3.8%KentuckyJobs YoY 0.0%Unemployment 4.7%LouisianaJobs YoY +1.8%Unemployment 4.0%MaineJobs YoY +0.1%Unemployment 3.3%MarylandJobs YoY -0.5%Unemployment 3.9%MassachusettsJobs YoY +0.4%Unemployment 4.3%MichiganJobs YoY 0.0%Unemployment 5.0%MinnesotaJobs YoY +1.2%Unemployment 4.5%MississippiJobs YoY +0.6%Unemployment 3.3%MissouriJobs YoY +1.0%Unemployment 3.6%MontanaJobs YoY -1.0%Unemployment 3.1%NebraskaJobs YoY +0.4%Unemployment 2.9%NevadaJobs YoY +1.6%Unemployment 4.7%New HampshireJobs YoY +0.3%Unemployment 2.6%New MexicoJobs YoY +1.3%Unemployment 4.7%North DakotaJobs YoY +0.2%Unemployment 2.2%OhioJobs YoY +0.3%Unemployment 3.4%OklahomaJobs YoY +0.8%Unemployment 4.2%OregonJobs YoY -0.1%Unemployment 5.0%PennsylvaniaJobs YoY +0.7%Unemployment 3.6%Rhode IslandJobs YoY -0.1%Unemployment 3.6%South CarolinaJobs YoY +2.3%Unemployment 4.0%South DakotaJobs YoY +0.4%Unemployment 2.0%TennesseeJobs YoY +0.8%Unemployment 3.4%UtahJobs YoY +1.5%Unemployment 3.5%VermontJobs YoY -0.1%Unemployment 2.6%VirginiaJobs YoY -0.6%Unemployment 3.6%WashingtonJobs YoY +0.7%Unemployment 4.8%West VirginiaJobs YoY 0.0%Unemployment 4.0%WisconsinJobs YoY +0.4%Unemployment 3.2%WyomingJobs YoY +0.9%Unemployment 3.0%
All states
Data center finance / NEWS

Behind Anthropic’s IPO Is a $19 Billion Data Center Lease in Kentucky

The Claude maker’s Nasdaq debut puts a spotlight on a 20-year lease at a former aluminum smelter, where Google has agreed to conditional credit support and construction is underway.

A row of buildings on Main Street in downtown Hawesville, Kentucky; not the data center project.
Main Street in downtown Hawesville, Kentucky, in July 2011. File photo of the community; the TeraWulf data center site is not shown. Photo: Nyttend / Wikimedia Commons · Public domain. Wikimedia downscaled version; display crop.

Anthropic began trading on Nasdaq Thursday after pricing its initial public offering at $83 a share. The offering totaled about $81 billion before underwriting discounts, including shares sold by existing investors. But one of the clearest examples of the real estate behind the IPO is in Hawesville, Kentucky, where the company signed a lease in July for two decades of data center capacity at a former aluminum smelter. IPO prospectus · Trading debut

TeraWulf, the developer, puts contracted revenue from the initial 20-year term at roughly $19 billion. The lease covers three buildings and about 401 megawatts of capacity for computing equipment. TeraWulf says construction is underway, with the first building targeted for late 2027 and the third for the second quarter of 2028. The $19 billion is revenue contracted over the lease term, not the cost of constructing the campus or rent already collected. TeraWulf’s November project update

Why the former smelter matters

The project can reuse the switchyard and transmission lines that once served the aluminum plant, according to the utility’s filing. TeraWulf reports 482 megawatts of approved electric service, a separate measure from the 401 megawatts contracted for computing equipment. Google has agreed to backstop certain Anthropic obligations to support project financing. Under the agreements, each backstop takes effect when the final data hall under the corresponding lease commences service. Subject to the agreements, Google can take over the relevant lease or, in certain circumstances, allow it to terminate and pay a fee. Utility filing · Credit support filing

The property deal is only part of the bill

In its November 11 European prospectus, Anthropic disclosed about $900.9 billion in purchase and lease commitments, nearly all tied to computing and infrastructure. That total includes more than real estate. Its prospectus says it can contract for building capacity before making larger commitments for the chips inside. It had already announced a $50 billion U.S. infrastructure plan with Fluidstack in 2025, initially naming Texas and New York. That plan predates the IPO and is separate from the Kentucky lease. Anthropic’s 2025 announcement European prospectus

In Kentucky, the next milestone is physical: whether the first building is delivered on schedule. The tenant commitment, approved electric service and conditional credit support are documented. The computing capacity still has to be built.