On Friday, Anthropic closed an initial public offering that sold about $93.5 billion of stock at the offering price. That includes shares sold by existing holders and an extra allotment bought by underwriters. It is an enormous deal. But in the same offering paperwork, the maker of Claude gives investors a much bigger number: $900.9 billion in contractual obligations, almost all related to compute and infrastructure. Anthropic’s closing announcement · Final prospectus
The two figures measure different things. One is the gross value of stock sold in a single offering. The other is a collection of obligations stretching over years, including cloud hosting, equipment and leases that have yet to begin. Anthropic estimates that $70.7 billion is due in the 12 months after Sept. 30. It also says about $186.2 billion of the total is tied to arrangements that can be terminated or depend on conditions before they start. That can mean a developer still needs financing, a facility or a permit. The total is not one bill due today, or $900.9 billion in rent for buildings. Final prospectus
In Texas, the product is land with power
A lease in Corsicana, Texas, shows how those obligations can look on the ground. Riot Platforms’ quarterly filing identifies Anthropic as the tenant on a deal for land, powered building pads and supporting infrastructure designed to deliver 910 megawatts of capacity for computing equipment. Riot is responsible for building and delivering the site and power infrastructure. The tenant owes base rent on each block as it is delivered, not on the full 910 megawatts from day one. Riot is targeting the first delivery for June 2027 and full delivery for July 2028. Those are targets, not operating capacity today. The starting rate is $130 per kilowatt per month of delivered capacity. At that rate, all 910 megawatts would represent about $118 million in monthly base rent before escalators or credits. That is a calculation, not current rent collections. Riot’s quarterly filing
The Kentucky deal we covered earlier has a different structure. At Hawesville, TeraWulf agreed to supply Anthropic with about 401 megawatts at a purpose-built campus. TeraWulf expects roughly $19 billion in revenue over the initial 20-year term, and a later filing says rent begins as individual data halls are delivered. It also says Google agreed to backstop certain obligations under the Kentucky leases, not all of Anthropic’s spending commitments. The backstop becomes effective upon commencement of the last data hall under the corresponding lease. The $19 billion is the landlord’s estimate for that lease, not a property sale price or a number to add to the prospectus total. TeraWulf lease announcement · TeraWulf November filing
For landlords and lenders, the IPO is the headline. The dates when those pads and halls actually start earning rent are the numbers to watch next.