HUNT COUNTY, Texas | Nov. 17, 2026 — Giga Energy said Tuesday it signed a 10-year lease valued at $1 billion with a U.S. AI cloud provider for a data center under construction east of Dallas. The Houston-based developer said it broke ground in July on the roughly 30-acre campus, called Project Marl, and plans to own and operate it after it opens. The company is targeting spring 2027 for service. Giga Energy announcement
The announcement matches the headline terms that a public relations firm outlined to the local news outlet The Lens in October without naming the developer. Giga did not disclose the tenant, the payment schedule or how the $1 billion breaks down. The figure represents the company’s stated value of the lease over its term; it does not establish a property valuation or an annual rent. October reporting by The Lens
What Texas records show
A Texas construction registration lists Giga AFM LLC as the owner of the BT Gateway Data Center near Royse City, in Hunt County. It describes a 100,000-square-foot building with an estimated construction cost of $384 million. The Texas Comptroller’s registry also lists Giga AFM as the owner of a data center called Project Royse and identifies The Constant Company LLC as its occupant and operator. Constant identifies Vultr as its cloud computing brand. The records point to a possible connection, but they do not establish that either registered project is Project Marl or that Constant signed the lease Giga announced Tuesday. Texas construction registration · Texas Comptroller’s registry · Constant’s Vultr brand
The spring opening hinges on power
Giga says it will tap unused electrical capacity through dedicated infrastructure designed to avoid drawing on the distribution capacity that serves existing homes and businesses. It also says the closed-loop cooling system won’t use municipal water or groundwater to cool the computing equipment, though the site will still need water for sinks and restrooms. The announcement did not give a utility energization date. Giga Energy announcement
Those details matter in a county that asked Texas lawmakers in June for authority to temporarily pause certain large developments, citing potential strain on water supplies, roads and emergency services. Separately, Core Scientific disclosed that it paid about $232.5 million for land and related power arrangements in Hunt County expected to support roughly 430 megawatts of gross utility capacity. Hunt County resolution · Core Scientific filing
Building modules in a factory can shorten the construction schedule. It can’t substitute for a live power connection. With a customer lined up, the next date to watch is when the site can actually take power and begin serving that customer.
Published by The Basis. Research dates, source references and illustrative assumptions are retained from the original article.